Tuesday, September 27, 2011

The first (few hundred) blocks

Quick update on progress on site over the last week or so...

Blockwork has started on Terrace A, although we are now waiting for the lintels which will bridge over the service entries and the engineering bricks to arrive on site.  Finished floor levels will be three courses of engineering bricks above the top of the blockwork as seen here.

The common garden area to terrace A is small but has a lovely outlook



See the extra wide cavity, which for those of you in the know, will give a wall U-value of between 0.10 and 0.12

The Common House blockwork is ready to go. Note that the front of building 2 has now been pulled down to make way for the Children's room, toilets, laundry and guest rooms.  The floor will be lowered to provide level access

Meanwhile at terrace D the building platform is being levelled.  A report on the safety of the rock face to the right is pending - we plan to leave it looking as natural as possible

And at Heron Bank, the pile of rubble just gets bigger and bigger.










Jon