The roof structure on Terrace A is now virtually complete, ready for tiling to start next week |
This close up shows the progress on the timber framed south elevations. Almost ready to start fitting windows. |
A few days of warmer dry weather has allowed the block work on Terrace F to get moving again |
Unfortunately we are nowhere near being able to reopen the top public footpath, the weather related delays having taken their toll. |
This is Terrace F from the top. Plot 28, to the right is still available. |
The roof is now being installed on the Common House |
Note the different colours of blocks on the upstairs flat bed loft walls. The paler thermal blocks transmit less heat and will prevent an unacceptable thermal bridge through the roof. |
Inside the Mill building, work is well underway to create the showers and toilets |
...although the discovery of a couple of unexpected windows means that a few minor changes to the works specification have been required. |