| Scaffolding going up on terrace C as the blockwork gets going |
| Terrace B roof trusses to the rear. No more progress on the slope stabilisation though as the material is still too wet |
| The gabions need to be built up at the same rate as the slope so that it all ties together |
| The Common House is being roofed ready for its sedum covering |
| Inside unit 6u, an upstairs flat |
| Upstairs windows are now being fixed - doors are coming from the factory in Latvia next week, and then Terrace A can be made weathertight. Rendering and interior works can then progress. |
| The Common House roof from Terrace A |